US 35 Corridor Improvements

Greene County

In 2004, the Miami Valley Regional Planning Commission in cooperation with ODOT, completed the Greene 35 Corridor Study, to recommend a strategy to convert the section of US35 between the North Fairfield Interchange and the Xenia Bypass to a limited-access facility (see study area).

The current project, GRE-35-4.26, focuses on the recommendations of the Corridor Study following ODOT's Project Development Process (PDP). The PDP provides a framework for decision making to take a project from the planning stages to construction. The project is currently in the environmental analysis and preliminary engineering phases.

A vision statement and team charter document has been established to guide the development of the project. The team charter document summarizes the project vision, critical success factors, and communication guidelines. Endorsement of the charter by the project team and stakeholders represents a commitment to assure successful project implementation.

Project Vision

Completing the upgrade of GRE-35 to a limited access highway will improve travel times on both the highway and many local streets while reducing accident rates. The fiscally responsible project should reduce air pollution, preserve nearby parks and natural areas, and support the retention and expansion of regional business. GRE-35 will satisfy the needs of the traveling public and be a source of pride for the project team and the community.

Project Documentation

Team Charter Document (Adobe Acrobat Reader:64 kb)